A Chip Company Releases AIDC Energy Storage Certification Standards. Why NVIDIA? Computing Power Reshapes Power Supply Logic. Who's in the Lead and Who's Left Out?

marsbitXuất bản vào 2026-06-23Cập nhật gần nhất vào 2026-06-23

Tóm tắt

NVIDIA has released a "Battery Energy Storage System Self-Certification Guide," setting strict technical standards for energy storage systems specifically for AI data centers (AIDC). The guide focuses solely on certifying the Power Conversion System (PCS), not the batteries, with 10 mandatory performance metrics and 12 validation tests requiring real-world and simulation comparisons. Key requirements include rapid dynamic response to AI workloads, high-frequency system telemetry, and detailed electromagnetic transient models. The move is driven by the extreme and fluctuating power demands of next-generation AI hardware. Modern AIDCs require energy storage systems to act as intelligent, controllable grid assets, not just passive backup, to manage instantaneous, massive power load shifts that traditional UPS systems cannot handle. This redefines the competitive landscape for energy storage providers, shifting focus from capacity and cost to advanced control capabilities and system integration. While the market potential is significant—with forecasts of hundreds of GWh in new demand by 2030—the certification creates a high barrier to entry. It requires proven PCS delivery volumes and credible plans for rapid capacity scaling, favoring established, well-resourced players. Early movers like Fluence (partnering with Siemens) and several Chinese companies have secured projects ahead of the standard, but new entrants must now navigate this rigorous, costly, and time-intensive certi...

Foresee Energy learned that NVIDIA recently released a "Self-Certification Guide for Energy Storage Systems," which sets 10 mandatory metrics, 12 items requiring actual measurements plus simulation comparisons, with measurement accuracy strictly defined at voltage ±0.2% and current ±0.2%. A graphics card company is drawing the entry line for the energy storage industry.

Most people's initial reaction is probably: You don't even manufacture energy storage equipment, what gives you the right to set the rules?

But in reality, as NVIDIA is redefining computing power, it's also redefining how data centers consume electricity.

From the GB200 in 2025 which first introduced the 800V HVDC architecture, to the Vera Rubin NVL72 in 2026 with a single cabinet power consumption approaching 225kW. In the Agentic AI era, thousands of GPUs within an AIDC can ramp from 10% to 100% power in milliseconds. For a 100MW AIDC, this could cause grid load to surge by tens of thousands of kilowatts instantaneously. Traditional UPS systems and diesel generators simply cannot keep up. While energy storage is being integrated into the top-level design of AI data centers, the method of its integration—through certification thresholds set by a chip company—leaves the entire industry both excited and uneasy.

01

Certification Boundary Drawn on the AC Side

It Tests the PCS, Not the Battery

The uniqueness of NVIDIA's guide lies in the fact that it focuses solely on the PCS (Power Conversion System). Battery capacity? Irrelevant. DC-side topology? Irrelevant. Battery cell type? Also irrelevant. The certification boundary is set on the AC side, with the PCS being the sole object of assessment.

Among the 10 mandatory metrics, "AI Buffer Dynamic Response" requires the system to avoid oscillations or control "chasing" during rapid power conversion; "Telemetry & Control" demands polling of all nodes at a 1Hz frequency, supporting 3 concurrent Modbus TCP connections; "Control Transparency" requires providing EMT (Electromagnetic Transient) models and impedance/admittance scan verification, and compliance with NERC reliability guidelines. All 12 items require both hardware measurements and simulation comparisons before submission for certification. Beyond the technical threshold, manufacturers must also submit their PCS delivery volume over the past 12 months and a viable plan to achieve a 10x production expansion within 24 months.

In a technical blog, NVIDIA stated: A BESS (Battery Energy Storage System) is an "intelligent, controllable electrical asset," not a passive storage warehouse. The complexity of a BESS in an AIDC factory far exceeds capacity rating—it's a control system deeply interacting with the grid, requiring full-stack co-design of hardware and software, rather than "determining capacity first, then matching control." Hardware specs alone cannot solve control issues; rapid telemetry, real-time analytics, and coordinated control architecture are key to the design. No matter how large the battery, poor control logic means failure to pass certification.

This means the competition dimensions the energy storage industry has focused on in recent years—capacity and cost—become invalid under this standard.

02

The Game Has Changed

Those Who Jumped the Gun Are Already on the Road

In early June, Siemens officially released its reference electrical and power architecture design for the NVIDIA DSX Vera Rubin NVL72 platform. Fluence's SmartStack battery energy storage system was incorporated, becoming the only explicitly designated battery storage partner in this reference design, which was met with a 43.8% stock surge on the same day. This reference design has a total facility capacity of 136MW, with IT load at 100MW. The SmartStack energy storage system configured by Fluence is 120MW/240MWh.

However, Fluence securing this position is less a victory in a technical bid and more a case of pre-emptive locking of industry chain influence. Fluence itself is a joint venture between Siemens and the American power company AES. Being included in the parent company's official reference design is essentially "niche inheritance." Other independent energy storage companies find it difficult to replicate this structural advantage.

With the release of NVIDIA's guide, the path has become clearer, but also dauntingly narrow. The market potential is not small, but are the competitors really enough? CLSA estimates that AIDC construction in China over the next five years will bring 125GWh of new demand for energy storage batteries. Guosheng Securities forecasts that just AIDC deployments in the US from 2026 to 2028 could drive incremental demand of 10GWh, 27GWh, and 39GWh, respectively. Morgan Stanley predicts that by 2030, AI data centers will generate 321GWh of annual new energy storage demand.

Some are already racing ahead. In February of this year, Nanjing Guanlong Power won a bid for a backup power project at an NVIDIA data center in Asia, supplying two sets of 1MW grid-forming energy storage converter integrated systems to replace diesel generators, enabling zero-delay seamless backup during power loss. WeiGuang Energy signed an agreement for the Changzhou Xinbei District, planning to build a solid-state transformer production base for AIDC scenarios over the next three years. Its "Xihe 2.0" system directly converts 10kV medium voltage to 800V DC, achieving a system efficiency of 98.6% and a volume only one-third that of a traditional UPS. According to Eastmoney.com, Sungrow Power had secured over 11GWh of AIDC energy storage orders by the first half of 2026. Trina Solar's energy storage business grew by over 300% year-on-year in Q1 2026, with overseas business accounting for over 90% of the total. In April, Far East Smarter Energy's orders involving smart battery storage and computing power/AI amounted to a combined 7.37 billion yuan.

However, all these projects broke ground before the formal release of the certification standards. After the standards are out, latecomers must follow the new rules from scratch.

03

The Threshold is Set

Who Can Pass, and Who Cannot?

The most brutal part of the certification guide is hidden in its final pages. Manufacturers must submit their PCS delivery volume from the past 12 months and a credible plan for 10x production expansion within 24 months. These two requirements alone shut out small manufacturers—they can't even gather the materials for certification, let alone provide delivery records or expansion commitments.

AIDC power supply energy storage systems involve multi-dimensional testing covering electrical safety, thermal runaway protection, and cybersecurity. The certification cycle, capital costs, and technical rectification difficulty are incomparable to those of typical commercial & industrial energy storage. A complete AIDC integrated energy solution isn't a single device certification; it's a combined verification of energy storage batteries, converters, power distribution equipment, and monitoring systems. It requires simultaneous completion of dozens of standard tests like UL1973 for battery cell safety, UL9540A for cabinet-level thermal runaway propagation, and IEC62443 for industrial network protection. The entire process typically takes 12 to 24 months, with cumulative costs for testing, rectification, and certification services reaching millions of RMB.

Price wars in the energy storage industry have escalated from competition at the "fen" level to the "li" level. NVIDIA's guide essentially draws a new starting line. Those lacking sufficient control capability don't even get a seat at the table. At the 2026 Two Sessions, National People's Congress representative Xu Yanming pointed out that AIDCs require energy storage systems to possess instantaneous high-current output capability and millisecond-level response speed. However, existing energy storage products still struggle to fully meet the high dynamic load demands in terms of rate performance, dynamic response, and long-term operational stability.

NVIDIA isn't trying to do the work of an energy storage association; it's drawing blueprints for its own factories. Whoever defines the computing power requirements has the right to define the power supply standards. This door has been opened, but whether one can step through depends on whether each company's PCS control algorithms are fast enough, their delivery records solid enough, and their expansion plans credible enough. Piling batteries higher won't solve this problem.

This article is from the WeChat public account "Foresee Energy," author: Zhao Jianan.

Tiền kỹ thuật số thịnh hành

Câu hỏi Liên quan

QWhat is the core focus of NVIDIA's 'Self-Certification Guide for Energy Storage Systems' for AIDC?

AThe guide focuses exclusively on certifying the Power Conversion System (PCS), not the batteries themselves. It sets stringent performance and control requirements for PCS, such as dynamic response, telemetry frequency, control transparency, and the need to provide historical delivery data and scalable production plans.

QWhy is NVIDIA, a chip company, setting certification standards for energy storage in data centers?

ABecause NVIDIA's high-power AI chips (like GB200, Vera Rubin NVL72) are redefining power consumption in data centers, causing extreme, instantaneous power load surges. To ensure the reliability of its AI data centers (AIDC), NVIDIA is defining the power supply standards. It dictates the energy storage performance requirements because it designs the primary power-consuming systems.

QAccording to the article, how does NVIDIA's standard change the competitive landscape for energy storage companies?

AIt shifts the competition from a focus on scale, capacity, and cost to a focus on high-level control technology, software-hardware integration, and proven delivery capabilities. Companies with advanced PCS control algorithms, strong delivery records, and credible expansion plans have an advantage. Smaller companies without these capabilities may be excluded.

QWhich company was highlighted as an early beneficiary of the trend towards AIDC energy storage, and why?

AFluence (a Siemens & AES joint venture) was highlighted. Its SmartStack BESS was designated as the sole energy storage partner in Siemens's official reference design for NVIDIA's Vera Rubin NVL72 platform. This advantage is described as 'ecological niche inheritance,' leveraging its structural ties within the industrial ecosystem, making it hard for independent companies to replicate.

QWhat are the major practical barriers for companies seeking NVIDIA's AIDC energy storage certification?

AMajor barriers include: 1) High technical requirements for PCS control and integration. 2) The need to submit 12 months of PCS delivery history and a credible 24-month plan for 10x production scale-up. 3) Lengthy (12-24 months) and expensive (potentially millions in fees) multi-standard certification processes covering electrical safety, thermal runaway, and cybersecurity for the entire energy system.

Nội dung Liên quan

Các doanh nghiệp khai thác tiền ảo đổ xô vào AI, nhưng Phố Wall lại hạ 'nhiệt' định giá, mùa báo cáo tài chính tiết lộ ai đang 'lội ngược dòng'?

Tác giả: Nancy, PANews Câu chuyện chuyển đổi sang AI của các công ty khai thác Bitcoin không còn mới và dần trở thành tiêu chuẩn ngành. Tuy nhiên, khi ngày càng nhiều công ty đổ vào lĩnh vực này, Phố Wall bắt đầu giảm bớt định giá cao cho câu chuyện chuyển đổi. Phân tích gần đây cho thấy phản ứng thị trường đang hạ nhiệt rõ rệt. Ngay cả các hợp đồng hosting AI lớn cũng khó lặp lại tác động kích thích thị trường như giai đoạn đầu. Trong khi đó, giá trị thương mại của dịch vụ hosting AI/HPC vẫn đang tăng. Điều này có nghĩa thị trường không còn mua câu chuyện chuyển đổi, mà bắt đầu tập trung vào chất lượng khách hàng, khả năng triển khai dự án, vốn đầu tư và dòng tiền thực tế. Đối với các công ty khai thác Bitcoin, chìa khóa đã chuyển từ "kể chuyện" sang "chứng minh mô hình kinh doanh". Báo cáo tài chính quý 2 tiết lộ sự khác biệt trong tiến độ chuyển đổi: - **Marathon Digital (MARA):** Doanh thu giảm, lỗ ròng mở rộng. Cơ sở hạ tầng AI/HPC vẫn đang xây dựng, chưa đóng góp doanh thu. - **Core Scientific:** Doanh thu tăng mạnh 109%. Doanh thu từ hosting AI/HPC chiếm 83% tổng doanh thu, trở thành động lực chính. Tuy nhiên, chi tiêu vốn cao và nợ tăng. - **TeraWulf:** Doanh thu từ cho thuê HPC chiếm 71% tổng doanh thu. Đã ký hợp đồng dài hạn lớn với Anthropic, nhưng vẫn ghi nhận lỗ ròng lớn. - **Hut 8:** Doanh thu tăng trưởng mạnh nhờ kinh doanh ASIC, đã hoàn thành thương mại hóa khuôn viên AI đầu tiên và ký được hợp đồng hosting lớn, nhưng vẫn thua lỗ. - **CleanSpark:** Doanh thu hoàn toàn từ khai thác Bitcoin, giảm. Điểm nhấn là hợp đồng cho thuê trung tâm dữ liệu 20 năm trị giá 66 tỷ USD, nhưng doanh thu từ dự án này sẽ chỉ bắt đầu từ cuối năm 2027. Nhìn chung, nhiều công ty vẫn đối mặt với doanh thu giảm, thua lỗ mở rộng và áp lực vốn đầu tư cao. Câu chuyện chuyển đổi vẫn còn khoảng cách để hiện thực hóa dòng tiền. Các nhà đầu tư ngày càng tập trung vào các chỉ số cụ thể như khả năng giao hàng, chất lượng khách hàng và năng lực tạo ra dòng tiền trong tương lai.

marsbit15 phút trước

Các doanh nghiệp khai thác tiền ảo đổ xô vào AI, nhưng Phố Wall lại hạ 'nhiệt' định giá, mùa báo cáo tài chính tiết lộ ai đang 'lội ngược dòng'?

marsbit15 phút trước

Cùng BlockBeats Xây Dựng Nền Tảng Thông Tin Tài Chính Thế Hệ Tiếp Theo

BlockBeats cam kết giúp người dùng hiểu rõ sự phát triển của công nghệ toàn cầu và biến động thị trường vốn thông qua thông tin thời gian thực, nghiên cứu chuyên sâu, phân tích dữ liệu và công cụ thông minh. Trong 7 năm, BlockBeats đã trở thành nền tảng tài chính công nghệ có ảnh hưởng tại thị trường Hoa ngữ. Chúng tôi đang xây dựng cổng thông tin tài chính cá nhân thế hệ tiếp theo, kết hợp dữ liệu thị trường tài chính toàn cầu, tin tức & sự kiện thời gian thực, nội dung nghiên cứu chuyên nghiệp và khả năng phân tích AI. **CƠ HỘI TUYỂN DỤNG:** BlockBeats tuyển dụng nhiều vị trí toàn thời gian và thực tập, với cơ hội làm việc từ xa. Văn phòng chính đặt tại Bắc Kinh. **Các nhóm và vị trí tuyển dụng:** 1. **Nhóm Tin tức Nóng:** Biên tập viên Thông tin Thị trường Toàn cầu - Theo dõi động thái thị trường tài chính, công nghệ; phân tích sự kiện quan trọng về AI, tài sản số, chính sách vĩ mô. 2. **Nhóm Báo chí & Nghiên cứu Chuyên sâu:** Nghiên cứu viên Tài chính Công nghệ - Thực hiện nghiên cứu, phân tích ngành, phỏng vấn chuyên gia về AI, tài sản số, các ngành công nghiệp mới. 3. **Nhóm Vận hành:** Chuyên viên Vận hành - Phụ trách vận hành mạng xã hội (Twitter, Telegram, Xiaohongshu), tăng trưởng người dùng, quản lý cộng đồng và phân tích dữ liệu. 4. **Nhóm Thương mại:** * Chuyên viên Thương mại: Thực thi hợp tác khách hàng, lập kế hoạch. * Chuyên viên Phát triển Thương mại Hải ngoại: Mở rộng thị trường nước ngoài, tìm kiếm đối tác và KOL. 5. **Nhóm Sản phẩm:** * Lập trình viên Front-end: Phát triển giao diện web với Vue.js/Next.js. * Lập trình viên Back-end: Phát triển hệ thống máy chủ với PHP/Python/Go. 6. **Nhóm Thị trường Dự đoán:** Nhà nghiên cứu/Tác giả Nội dung - Phân tích sự kiện thị trường dự đoán, hành vi trên chuỗi, tác động của sự kiện vĩ mô, địa chính trị, AI, Crypto. **Ứng tuyển:** Gửi CV và sản phẩm liên quan (nếu có) qua email hoặc Telegram trực tiếp cho HR, nêu rõ vị trí quan tâm (toàn thời gian/thực tập) và hình thức làm việc (từ xa/không). * Email: [email protected] * Telegram HR: @Jhy10vewh0

marsbit30 phút trước

Cùng BlockBeats Xây Dựng Nền Tảng Thông Tin Tài Chính Thế Hệ Tiếp Theo

marsbit30 phút trước

Một trong những người mua Bitcoin lớn đầu tiên, mua với giá 15 USD, đã hoạt động trở lại sau 10 tháng!

Một trong những nhà đầu tư Bitcoin đầu tiên, người đã mua BTC khi giá chỉ từ 10-15 USD, đã hoạt động trở lại sau khoảng 10 tháng không có động thái. Theo dữ liệu từ nền tảng phân tích on-chain Onchain Lens, "cá voi" này vừa chuyển 50 BTC (tương đương khoảng 3,22 triệu USD) sang một địa chỉ ví mới. Giao dịch này không trực tiếp là một lệnh bán, nhưng nó có đặc điểm tương tự các lần chuyển tiền trước đây của cùng nhà đầu tư. Trong quá khứ, nhà đầu tư này từng chuyển tài sản tới các dịch vụ tiền mã hóa tổ chức như FalconX hoặc các sàn giao dịch tập trung (CEX) sau các bước tương tự. Do đó, động thái mới nhất được xem là một dấu hiệu có thể cho thấy sự chuẩn bị cho một thương vụ bán OTC (giao dịch phi tập trung). Giao dịch OTC là phương pháp được các tổ chức và "cá voi" ưa chuộng để mua/bán khối lượng tài sản lớn mà không gây ảnh hưởng đáng kể đến giá thị trường. Tuy nhiên, các chuyên gia lưu ý rằng không nên đưa ra kết luận chắc chắn chỉ từ một lần di chuyển tài sản. Các nhà đầu tư lớn cũng có thể chuyển tiền vì lý do bảo mật, cập nhật chiến lược lưu trữ hoặc hợp nhất ví. Do vậy, việc chuyển tiền này không nhất thiết báo hiệu một đợt bán sắp diễn ra.

cryptonews.ru33 phút trước

Một trong những người mua Bitcoin lớn đầu tiên, mua với giá 15 USD, đã hoạt động trở lại sau 10 tháng!

cryptonews.ru33 phút trước

Bridge, công ty con của Stripe, gia nhập sổ đăng ký MiCA của EU sau khi được Luxembourg chấp thuận

Công ty Bridge Building, thực thể tại Luxembourg đứng sau công ty cơ sở hạ tầng stablecoin Bridge thuộc sở hữu của Stripe, đã chính thức tham gia sổ đăng ký Quy định về Thị trường Tài sản Crypto (MiCA) của Liên minh Châu Âu sau khi nhận được phê duyệt quy định từ Luxembourg. Việc bổ sung này nâng tổng số tổ chức phát hành token tiền tệ điện tử (EMT) được ủy quyền theo MiCA trong sổ đăng ký EU lên 42. Động thái này diễn ra vài tuần sau khi Bridge thông báo vào ngày 2/7 về việc đã đạt được ủy quyền Nhà cung cấp Dịch vụ Tài sản Crypto (CASP) theo MiCA và giấy phép Tổ chức Tiền tệ Điện tử (EMI) từ cơ quan quản lý tài chính Luxembourg. Các giấy phép này cho phép các doanh nghiệp trong EU xây dựng sản phẩm stablecoin và thanh toán trong khuôn khổ được quy định. Cùng bản cập nhật từ Cơ quan Quản lý Chứng khoán và Thị trường Châu Âu (ESMA) cũng bổ sung ba nhà cung cấp CASP mới từ Đức, nâng tổng số CASP được ủy quyền lên 324. Không có thay đổi nào đối với việc ủy quyền token tham chiếu tài sản (ART) và danh sách các công ty không tuân thủ. ESMA gần đây đã công bố các bản cập nhật sổ đăng ký MiCA thường xuyên hơn.

cointelegraph1 giờ trước

Bridge, công ty con của Stripe, gia nhập sổ đăng ký MiCA của EU sau khi được Luxembourg chấp thuận

cointelegraph1 giờ trước

Giao dịch

Giao ngay

Bài viết Nổi bật

Làm thế nào để Mua CHIP

Chào mừng bạn đến với HTX.com! Chúng tôi đã làm cho mua USD.AI (CHIP) trở nên đơn giản và thuận tiện. Làm theo hướng dẫn từng bước của chúng tôi để bắt đầu hành trình tiền kỹ thuật số của bạn.Bước 1: Tạo Tài khoản HTX của BạnSử dụng email hoặc số điện thoại của bạn để đăng ký tài khoản miễn phí trên HTX. Trải nghiệm hành trình đăng ký không rắc rối và mở khóa tất cả tính năng. Nhận Tài khoản của tôiBước 2: Truy cập Mua Crypto và Chọn Phương thức Thanh toán của BạnThẻ Tín dụng/Ghi nợ: Sử dụng Visa hoặc Mastercard của bạn để mua USD.AI (CHIP) ngay lập tức.Số dư: Sử dụng tiền từ số dư tài khoản HTX của bạn để giao dịch liền mạch.Bên thứ ba: Chúng tôi đã thêm những phương thức thanh toán phổ biến như Google Pay và Apple Pay để nâng cao sự tiện lợi.P2P: Giao dịch trực tiếp với người dùng khác trên HTX.Thị trường mua bán phi tập trung (OTC): Chúng tôi cung cấp những dịch vụ được thiết kế riêng và tỷ giá hối đoái cạnh tranh cho nhà giao dịch.Bước 3: Lưu trữ USD.AI (CHIP) của BạnSau khi mua USD.AI (CHIP), lưu trữ trong tài khoản HTX của bạn. Ngoài ra, bạn có thể gửi đi nơi khác qua chuyển khoản blockchain hoặc sử dụng để giao dịch những tiền kỹ thuật số khác.Bước 4: Giao dịch USD.AI (CHIP)Giao dịch USD.AI (CHIP) dễ dàng trên thị trường giao ngay của HTX. Chỉ cần truy cập vào tài khoản của bạn, chọn cặp giao dịch, thực hiện giao dịch và theo dõi trong thời gian thực. Chúng tôi cung cấp trải nghiệm thân thiện với người dùng cho cả người mới bắt đầu và người giao dịch dày dạn kinh nghiệm.

Tổng lượt xem 894Xuất bản vào 2026.04.21Cập nhật vào 2026.06.02

Làm thế nào để Mua CHIP

Thảo luận

Chào mừng đến với Cộng đồng HTX. Tại đây, bạn có thể được thông báo về những phát triển nền tảng mới nhất và có quyền truy cập vào thông tin chuyên sâu về thị trường. Ý kiến ​​của người dùng về giá của CHIP (CHIP) được trình bày dưới đây.

活动图片