Sinking Servers into the Sea? They're Dead Serious About This

marsbitPublished on 2026-05-20Last updated on 2026-05-20

Abstract

Sinking Servers into the Sea: A Serious Undertaking The article details China's launch of the world's first offshore, directly wind-powered, subsea data center in the East China Sea near Shanghai. This 1.95 billion yuan project houses over 2,000 servers in a submerged 10-meter-deep module. It is directly powered by a nearby offshore wind farm (over 95% green energy) and cooled by seawater. This innovative approach tackles the two core challenges of data centers: massive power consumption and heat dissipation. It achieves an exceptional Power Usage Effectiveness (PUE) of 1.15, far better than China's national average of 1.48, saving an estimated 61 million kWh of electricity annually. It also uses no freshwater and requires significantly less land. The concept builds upon earlier experiments, like Microsoft's Project Natick, which proved servers could reliably operate underwater with lower failure rates due to a stable, inert environment. The Shanghai project advances the model by co-locating with wind farms, simultaneously solving both the power source and cooling source problems in an economically viable way. This integration reduces infrastructure costs and eliminates grid transmission losses for the electricity used on-site. Looking ahead, the vision is to integrate data center modules directly into the foundations of future large-scale, deep-sea wind turbines. This synergy could create a distributed network of "compute factories" at sea, powered by cheap, local green ...

"Total investment of 1.6 billion yuan, PUE as low as 1.15, over 95% direct green power supply, saving 61 million kWh of electricity annually. The world's first offshore wind power direct-connected subsea data center begins operations in the East China Sea off Shanghai's Lingang."

The year is 2026. Everyone's happily using AI, but the people building computing power centers are going crazy. The demand for computing power is skyrocketing too fast, and cooling and power supply can't keep up. The industry has reached a stage where imagination is key. Some time ago, there was even talk of the concept of space-based computing power—launching data centers into outer space. And now, someone has actually thrown servers into the sea.

This isn't some futuristic concept we're introducing. It's already happened—an investment of 1.6 billion yuan, throwing over 2000 servers into the sea. Right now, in the East China Sea off Shanghai's Lingang, east of Xiaoyangshan Island, 10 meters underwater beneath an offshore platform, 192 cabinets are packed into a four-level underwater data hall, running computing power non-stop. The whole structure weighs 1950 tons, roughly equivalent to 1300 family cars. About 500 meters away, over 50 wind turbines are spinning, with wind power fed directly in—the green power supply rate exceeds 95%.

Let's look at a few figures first. PUE (Power Usage Effectiveness, a data center energy efficiency metric, closer to 1 is better): this subsea data center is 1.15 (this number is impressive, we'll come back to it later). The national average is 1.48. Freshwater consumption: Zero. Land area: 200 square meters. A land-based facility of the same scale would need 2000 square meters. After full-scale operation, it is expected to save 61 million kWh of electricity annually.

In other words, dunking servers in the sea not only didn't ruin them but also made them more energy-efficient, water-saving, land-saving, and even lowered the failure rate compared to being on land.

Recently, CCTV broadcast this news. After watching it, I dug into the backstory and found it far more interesting than what was reported.

Looking back, this is a path that has been explored and validated for years. Repeated verification was needed to ultimately ensure computing power could be safely thrown into the water. Looking forward, the grand endeavors of computing power centers and green energy happen to converge on this path—a major strategic move taking a crucial step.

It's worth telling from the beginning.

01: Why on Earth Sink Servers into the Sea?

Data centers can be complex or simple. Simplifying it, they need to solve two core problems: power supply and cooling.

Everyone knows servers need electricity. But many don't realize that the electricity used to cool servers might be almost as much as what the servers themselves consume.

The industry has a core metric for measuring data center energy efficiency called PUE, Power Usage Effectiveness. The calculation is straightforward: the total electricity used by the entire data center divided by the electricity used by IT equipment (servers, storage, networking). If the PUE is 2, it means for every 1 kWh the server burns to compute, the air conditioning and other supporting facilities burn another 1 kWh to cool it and keep it running.

Ideally, PUE should be 1, meaning all electricity goes into computing, with none wasted on cooling. But in reality, it can never reach 1, only approach it infinitely.

The average PUE for data centers across China is roughly 1.48. In other words, for every 3 kWh of electricity burned in Chinese data centers, about 1 kWh is used for air conditioning.

In 2024, global data center electricity consumption was approximately 415 terawatt-hours, accounting for 1.5% of total global electricity use. The IEA (International Energy Agency) predicts this number will more than double to 945 TWh by 2030. And that's just the energy consumption of traditional data centers. With the advent of AI, things have gotten even more exaggerated.

A standard CPU server used to consume about 300 watts. Replaced by a GPU server for AI training, the same rack might consume 3000 watts—a tenfold increase. The IEA report states that electricity consumption for AI-specific servers is expected to grow by 30% annually.

Someone with 20 years in the data center industry gave me a vivid picture: For an office building, the air conditioning units on the roof are sufficient for the whole building. But if you convert that building into a data center, cooling requirements increase exponentially. The area occupied by air conditioning and power equipment could even surpass that of the servers themselves. Eventually, filling the roof and the square below with AC outdoor units might still not be enough to dissipate the heat.

That's why the global data center industry has been pondering the same thing for years: how to find cheaper cooling sources. The answers are surprisingly consistent: go to nature.

Facebook once tried building data centers in high-latitude North America, as close to the Arctic Circle as possible, leveraging naturally low temperatures. A few years ago, Tencent built a data center inside a cave in Guizhou, where temperatures are constant year-round. In this matter, the primary siting criterion for big companies isn't transportation or talent; it's wherever it's cool.

China's "East Data West Computing" project follows the same logic: building data centers in Inner Mongolia, Guizhou, Gansu, etc. The west has electricity—cheap coal power and abundant new energy; the weather is cold—places like Ulanqab are below zero most of the year, offering strong natural cooling. The eight computing hubs and ten data center clusters essentially chase cheap electricity and free cooling westward.

But what about eastern cities?

Places like Shanghai, Shenzhen, and Beijing are precisely where computing power demand is strongest. Financial transactions, AI inference, cross-border data processing—many services are extremely latency-sensitive. Data can't always be routed to a cave 2000 kilometers away in Guizhou, computed, and sent back. Yet these cities happen to have the most expensive land, the tightest energy consumption quotas, and scorching hot summers.

Hence, the sea.

Seawater has an average annual temperature of only about 15 degrees Celsius, with extremely strong fluidity, offering cooling capacity dozens of times greater than lake water. Moreover, offshore wind power is undergoing large-scale construction, placing electricity right next door. Cooling source and power source—the two things data centers need most—are both available offshore.

Logically speaking, sinking servers into the sea is actually the most natural answer.

02: How Many Steps to Get Computing Power into the Sea?

Putting data centers on the seabed wasn't a Chinese idea first.

In 2015, Microsoft launched a project called Project Natick. The first experiment was quite simple: throw one down and see if it breaks. They sank a cylindrical sealed capsule about 2.4 meters in diameter to the Pacific seabed, containing servers, and ran it for 105 days to see if servers would actually work underwater.

The conclusion: yes.

In 2018, Microsoft moved to a second round with a formal deployment. Off the coast of Scotland's Orkney Islands, they sank a sealed container holding 864 servers to about 35 meters deep in the North Sea. Powered by local tidal and wind energy, cooled naturally by seawater, and then left alone.

Two years later, in 2020, Microsoft retrieved the unit from the seabed. Upon opening it, the data was astonishing.

Of the 800-plus underwater servers, only 6 had failed—a failure rate of about 0.7%. Meanwhile, Microsoft had a control group on land—135 servers running for the same two years. Eight failed, a failure rate of nearly 6%. The underwater failure rate was about one-eighth of that on land.

This was a counterintuitive result. Microsoft's explanation: The sealed capsule was filled with dry nitrogen—no oxygen, no humidity, no dust, no vibrations or temperature fluctuations from people entering and leaving. The servers operated in an almost sterile environment, significantly slowing hardware aging.

No one touching, no one looking, no dust, no one opening the door and walking in—instead, nothing went wrong. A place completely devoid of humans might just be the servers' ideal working environment.

Microsoft's experiment proved one thing: seabed cooling is feasible. What followed next was done by the Chinese.

In 2020, Hi-Target, a domestic listed company specializing in marine equipment, acquired a Canadian deep-sea equipment team. This team had previously been involved in the engineering work for Microsoft's Natick project. More importantly, they had over 20 years of experience in deep-sea fields. The know-how accumulated through that experience was crucial: what microorganisms grow where, the flow and geological conditions of different sea areas, how to design joints to last 20 years underwater without problems.

With this technical foundation, the first commercial subsea data center landed in Hainan.

Located in Lingshui's Qingshui Bay, Hainan, about 3 kilometers offshore at a depth of 40 meters. The design involved sinking a sealed canister to the seabed, connected to an onshore control station via submarine cable, using natural seawater cooling. Trial operations began in 2022.

After running for over three years, several key figures emerged. PUE less than 1.2, far better than the national average of 1.48. Cooling energy consumption saved over 90%, meaning annual electricity savings of about 3 million kWh, freshwater savings of about 15,000 tons, and an onshore footprint of only 400-500 square meters—roughly one-fifth of a land-based facility of the same scale.

It might sound like moving data centers underwater solves everything, but it's far from that.

For the Hainan generation, the cooling source problem was solved, and costs were validated, but the power source remained a短板. Over 70% of Hainan's grid relies on thermal power. The subsea data center uses municipal power from shore, requiring a submarine cable costing tens of millions of yuan. Daily operating costs are indeed low, but factoring in the heavy upfront capital investment during construction, the economics weren't great. Moreover, relying on thermal power wasn't green enough in the long run.

How to secure both cooling source and power source simultaneously? That's where the next step, Shanghai, comes in.

The Shanghai project follows a completely different approach: Located in the East China Sea off Lingang, east of Xiaoyangshan Island, just 500 meters from an existing 200-megawatt offshore wind farm. Wind power is directly fed into the data center via submarine cable, bypassing the land grid entirely, using genuine green power. Both cooling source and power source are finally solved together.

The crucial change lies in the cost structure. The Hainan generation required building its own shore station, laying cables, pulling networks—these infrastructure components accounted for a large proportion of the total investment. For the Shanghai generation, the shore station, cables, network, even some electrical equipment already existed at the wind farm site and were directly repurposed. This alone reduced investment by tens of percent.

The reason this journey took so long involves difficulties beyond technology, because this is something almost no one has done before, requiring the establishment of many standards from scratch.

First, environmental protection. A little-known fact: environmental standards for marine projects are much stricter than on land.

When you put a continuously heat-emitting object in the sea, effective heat dissipation is called cooling; ineffective dissipation turns it into an underwater heater. Someone previously tried using lake water to cool a data center, pumping cold lake water up for cooling and discharging it back. The result was a rise in lake temperature. While it didn't boil the fish, fish growth rates noticeably accelerated, disrupting the ecological balance—environmental standards were not met.

Marine standards are even stricter. Practitioners tell us that on this detail, environmental regulations require that the seawater temperature change around the data center (roughly within 1 meter) cannot exceed 0.1 degrees Celsius. 0.1 degrees—that precision is already demanding. But just meeting the standard isn't enough; you also need continuous monitoring capability and contingency plans for extreme situations. Not everyone possesses these capabilities.

Hailan Cloud, the company behind this project, is a subsidiary of Hi-Target, a listed company in the marine technology field. The parent company has years of experience in marine observation, subsea equipment, and maritime communications. If a company without marine engineering background attempted this, they might be stuck at the environmental hurdle alone.

Then there's the server side. Those willing to throw expensive servers into the water must truly trust the solution. This equipment isn't cheap; ruining it would be genuinely painful. Moreover, such projects inherently require every hardware component to be highly reliable. You can't expect to send someone down frequently to replace cards; it's very troublesome.

For various reasons, this project ultimately brought together major players from different fields across the chain. For instance, Shenergy, operating the wind farm, a major player in East China's energy sector; Shanghai Electric, the established industrial group, responsible for servers here; telecommunications handled by Shanghai Telecom, self-explanatory. In summary, marine engineering, energy supply, computing operations, server manufacturing—all assembled here. If one link fails, the whole endeavor falls apart.

03: Wind + Computing Power, How Big Is the Potential?

Looking further ahead, even the Shanghai project is just a beginning. What truly makes this path seem to have vast potential is its future integration with large-scale, far-offshore wind farms.

Shanghai is planning a deep-sea offshore wind farm with a total capacity of 4300 megawatts. Currently, a medium-to-large data center in Shanghai typically has a capacity around 20 megawatts. This means the generating capacity of this single wind farm could theoretically power over 200 medium-to-large data centers.

Of course, not all would go to data centers. But a relatively conservative proportion has been calculated: taking about 15% of the wind farm's maximum generating capacity is sufficient to supply a large-scale offshore computing cluster. What does 15% mean? Even when the minimum number of turbines are spinning, this portion of electricity is stable—no need for additional energy storage, no worry about fluctuations. It's the best kind of power.

Calculating based on this proportion, 15% of 4300 MW is approximately 600 MW. A 600 MW computing center, located offshore, directly supplied by green power, naturally cooled by seawater.

There's an important economic calculation here: Far-offshore wind farms are over a hundred kilometers from shore. Transmitting electricity from sea to land incurs transmission losses exceeding 10%. But computing power doesn't require transmitting electricity. Converting electricity directly into computing power at sea and sending the computed results back via fiber optics involves almost zero transmission loss. Electricity loss is over 10%, data loss is nearly zero. Both involve bringing something back from the sea; sending bits is far more economical than sending electrons.

Thinking even further. The foundation of an offshore wind turbine is called the tower or monopile—the large cylinder inserted into the seabed. Offshore wind turbines are getting bigger, with a single turbine's power increasing from 2-3 MW on land to 12 to 20 MW offshore. The tower diameter has also grown, now around 18 to 20 meters.

An 18 to 20 meter diameter cylinder, hollow inside, offers considerable space, but no one previously thought about what could be done inside.

What if, when constructing the wind farm, space was reserved inside to place servers? No need to build additional structures, lay extra cables. The wind farm's power supply facilities, submarine cables, network connections already exist. It's like building the server room while constructing the house.

Calculated this way, overall construction costs could drop by tens of percent compared to land-based facilities, not even counting electricity prices. If the cost of power consumed locally at the far-offshore site could be negotiated down to around three or four cents per kWh, overall operating costs could drop another notch.

A single wind turbine: blades spinning above generating electricity, servers running inside the column below. Each turbine scattered across the sea surface becomes a mini computing factory—no grid power, no freshwater, no human maintenance required. Perfect.

This sounds like science fiction, but the underlying logic holds at every step. Reaching this point, you realize the grand undertakings of energy and computing power interlock seamlessly. Wind power needs local consumption to improve economics; computing power needs cheap green electricity and free cooling. Two endeavors, originally on separate paths, converge at sea.

China has a significant advantage in pursuing this: offshore wind power. China possesses the world's largest installed offshore wind capacity, the lowest power generation costs, and the most mature construction supply chain. If anyone can pioneer the integration of computing centers with offshore wind, it's highly likely to be in China.

"East Data West Computing" goes west, chasing coal and cold. Now, someone is heading east, chasing wind and sea. Two routes, solving the same problem: letting computing power use the cheapest electricity and the freest cooling.

This article is from the WeChat public account "Cool Play Lab," author: Cool Play Lab

Related Questions

QWhat are the two core challenges that data centers primarily need to address, and how does the seabed data center in Shanghai tackle them?

AThe two core challenges are power supply and heat dissipation. The Shanghai seabed data center addresses these by being deployed near an offshore wind farm, using direct green wind power supply (over 95% green electricity), and utilizing the naturally cool (around 15°C) and highly mobile seawater for efficient, passive cooling.

QWhat is PUE and why is the PUE value of 1.15 for the Shanghai seabed data center considered significant?

APUE (Power Usage Effectiveness) is a key metric for data center energy efficiency. It is calculated by dividing the total power used by the entire data center by the power used solely by the IT equipment (servers, storage, network). A value closer to 1 indicates higher efficiency. The PUE of 1.15 for the seabed center is significant because it is much lower than China's national average of 1.48, meaning far less energy is wasted on cooling and supporting infrastructure compared to traditional land-based data centers.

QWhat surprising finding did Microsoft's Project Natick reveal about server reliability in an underwater environment?

AMicrosoft's Project Natick found that servers deployed in a sealed, nitrogen-filled underwater capsule had a remarkably lower failure rate. After two years, only about 0.7% of the 864 servers failed, compared to a nearly 6% failure rate in a comparable land-based control group. This was attributed to the stable, vibration-free, oxygen-free, dust-free, and human-interaction-free environment.

QWhat is the key economic and technical advantage proposed for co-locating future data centers within the support structures (monopiles) of large offshore wind turbines?

AThe key advantage is the significant reduction in construction and operational costs. By integrating the data center space into the wind turbine's monopile during construction, there is no need for separate foundations, dedicated power cables, or complex grid connections—the wind farm's existing infrastructure is reused. This, combined with access to cheap, on-site green power and free seawater cooling, could drastically lower the total cost of ownership for the compute power.

QHow does the 'computing power to the sea' strategy complement China's broader 'East Data West Computing' project?

ABoth strategies aim to solve the same fundamental problem: providing compute power with cheap electricity and free cooling. 'East Data West Computing' moves data centers inland to western regions for access to cheaper coal power and cooler climates. The 'computing power to the sea' strategy moves eastward to coastal waters, chasing abundant offshore wind power (green electricity) and the massive heat dissipation capacity of the ocean. Together, they offer dual pathways to build efficient, sustainable, and cost-effective national computing infrastructure.

Related Reads

After Three Consecutive Quarters of Decline, Can the Crypto Market Find a Window for Stabilization in Q3?

The cryptocurrency market has just concluded its worst-performing quarter since 2022, with total capitalization dropping 12.6% to $2.1 trillion. All core metrics indicate capital is leaving the sector, not just rotating within it. Bitcoin fell 14.2% and Ethereum dropped 25.4% in Q2, breaking their previous correlation with US tech stocks. A key driver is the reversal in US spot Bitcoin ETF flows, which saw a net outflow of approximately $4.67 billion in Q2, including a record monthly outflow near $4.5 billion in June. While recent data suggests long-term holders are accumulating again, sustained ETF outflows mean continued selling pressure. Market focus is now singularly on the Federal Reserve. The upcoming July FOMC meeting is seen as the most critical event for Q3. A dovish signal could support Bitcoin reclaiming a $68,000-$84,000 range, while a hawkish stance might establish a new trading band around $50,000-$56,000. Additionally, regulatory uncertainty persists, with the progress of the crucial *CLARITY Act* stalling in the Senate, reducing its perceived 2026 passage probability to 40-45%. Despite the broad downturn, a few sectors showed growth. Prediction markets saw nominal volume surge 48.7% year-over-year to $113.8 billion, and tokenized collectibles transaction volume rose 143% quarterly to $1.4 billion. The Real-World Asset (RWA) tokenization sector also continued steady growth, now representing ~$28.1 billion in on-chain value. The market's foundation for an extreme crash appears limited, with Bitcoin price hovering near its 200-week moving average. However, the trading paradigm has shifted from narrative-driven speculation to decisions based on price action, policy developments, and interest rate expectations, making a broad sentiment-driven rally unlikely in the near term.

marsbit2h ago

After Three Consecutive Quarters of Decline, Can the Crypto Market Find a Window for Stabilization in Q3?

marsbit2h ago

BIT Trading Moment: BTC Still Suppressed by Weekly 200 EMA, Rejection May Restart Decline; Storage and Semiconductors that Surged Last Night Begin Falling in Evening Trading

**Crypto & Stock Market Wrap: Bitcoin Tests Resistance, Stocks Retreat After AI Surge** Bitcoin consolidates around $66,000, facing key resistance near $68,000—an area seen as a major psychological and technical hurdle where previous rallies have failed. Analysts note the cryptocurrency is caught between its 200-week moving average (~$63,333) and 200-week EMA (~$68,328). A clear break above $68k is needed to signal a stronger bullish trend, while a rejection could lead to a retest of $63k support. Market sentiment remains cautious, with low futures open interest pointing to a low-liquidity rebound rather than a full bull market. Bitcoin spot ETFs saw another $203 million inflow. US stock futures pointed lower after a strong Tuesday session led by a massive rebound in semiconductors and memory stocks. The rally was fueled by renewed optimism about AI-driven hardware demand, with Micron, SanDisk, and SK Hynix surging. However, those gains reversed in pre-market trading. Super Micro Computer (SMCI) soared over 20% after hours on strong guidance and a record backlog. Other standouts included Rocket Lab and nuclear energy plays Oklo and X-Energy. Rising oil prices (Brent above $91) and climbing Treasury yields (10-year near 4.64%), however, are reigniting inflation concerns and acting as a headwind for equities. In Asia, markets were mixed. South Korea's KOSPI pared early gains to close slightly higher as semiconductor stocks like SK Hynix gave back initial surges. Japan's Nikkei edged lower as the yen hit a fresh 38-year low against the dollar, raising fears of potential market intervention. Key events to watch include the Samsung Galaxy launch, AMD's AI event, and a slew of major tech earnings from Alphabet, Tesla, and IBM after the close on Wednesday, followed by the ECB meeting and Intel's earnings on Thursday.

marsbit2h ago

BIT Trading Moment: BTC Still Suppressed by Weekly 200 EMA, Rejection May Restart Decline; Storage and Semiconductors that Surged Last Night Begin Falling in Evening Trading

marsbit2h ago

Former CFTC Chairman, Circle President Tarbert: Preaching Long-Termism While Cashing Out $30 Million Himself

Former CFTC Chairman and Circle President Heath Tarbert has consistently advocated for a long-term vision in public, urging patience from investors as Circle’s stock price has fallen significantly from its peak. However, it has been revealed that since Circle’s IPO, Tarbert has continuously sold his CRCL shares through pre-arranged trading plans, cashing out approximately $30 million, without making any public market purchases. This contrast between his public messaging and personal actions has drawn criticism. Tarbert joined Circle in July 2023 as Chief Legal Officer, leveraging his regulatory experience to help guide the company through its IPO and expansion. Despite promoting stablecoins as long-term infrastructure, he established a 10b5-1 trading plan just before Circle went public, leading to substantial stock sales over the following year. In March 2026, he initiated another plan to sell more shares. His career trajectory highlights a pattern of moving between high-level regulatory roles and influential positions in the financial sector. After resigning as CFTC Chairman in early 2021, he joined Citadel Securities as Chief Legal Officer just 27 days later, during a period of intense regulatory scrutiny for the firm. He later joined Circle, aiding its efforts to navigate regulatory challenges for its public listing. While Tarbert's expertise in policy and compliance is valuable to companies like Circle, his actions—advocating long-term confidence while personally divesting—raise questions about the alignment between his public statements and his private financial decisions, leaving investors who followed his advice to bear the market risks.

marsbit2h ago

Former CFTC Chairman, Circle President Tarbert: Preaching Long-Termism While Cashing Out $30 Million Himself

marsbit2h ago

Gate Research Institute: The 'Wall Street-ization' Wave of Crypto Financial Products – Competition or Integration?

The article titled "Gate Research Institute: Are Crypto Financial Products Sparking a 'Wall Street' Wave—Competition or Convergence?" explores the evolving relationship between the crypto ecosystem and traditional finance (TradFi). The piece begins by reflecting on Bitcoin's original 2009 vision of decentralization, disintermediation, and moving away from banks. It then contrasts this with the 2024 landscape, where key crypto assets like Bitcoin are increasingly held through Wall Street products like ETFs issued by giants like BlackRock. The article questions whether this signifies that TradFi is systematically taking over the rights to issue, price, custody, and distribute crypto financial assets. The core argument is that this is not a zero-sum takeover but rather a bidirectional convergence where each side addresses the other's weaknesses. Crypto offers 24/7 global markets, programmable settlement, and open access but lacks compliant channels, institutional-grade custody, deep fiat liquidity, and mainstream distribution. TradFi possesses these but is constrained by legacy systems, limited operating hours, and slow settlement. Two primary convergence paths are highlighted: * **Path A (CEX to TradFi):** Exemplified by Gate, which has progressed from offering tokenized stocks and CFDs to providing direct, real stock trading (US, Hong Kong, South Korea) within its platform, using USDT. * **Path B (TradFi to Crypto):** Exemplified by Robinhood, which has integrated crypto trading, acquired exchanges like Bitstamp, and is moving traditional assets like stocks onto the blockchain via tokenization and its own Layer 2. Both paths are ultimately competing to become the next-generation, unified financial account—a "super account" where users can seamlessly trade cryptocurrencies, stocks, ETFs, RWA (Real World Assets), and tokenized treasury products in one interface. The growth of RWA and tokenized treasuries (e.g., BlackRock's BUIDL) is presented as the asset-layer fusion, providing stable, yield-bearing assets on-chain and acting as a bridge between the two worlds. In conclusion, the "Wall Street-ization" of crypto is framed as a mutual transformation. Decentralized ideals persist in the protocol layer, while at the application layer, a more efficient, global, and accessible unified capital market is emerging from this convergence. The future competition lies not between crypto exchanges and stockbrokers, but between platforms vying to offer the most comprehensive asset coverage, liquidity, and user experience within a single account.

marsbit2h ago

Gate Research Institute: The 'Wall Street-ization' Wave of Crypto Financial Products – Competition or Integration?

marsbit2h ago

Trading

Spot
活动图片