Company Cipher Digital (NASDAQ: CIFR) announced its intention to issue new zero-coupon convertible bonds totaling $850 million, with a maturity date in 2032. This was announced on Tuesday, October 13, just three weeks after the company agreed to cover cost overruns of $359.3 million at its Barber Lake data center in Texas.
Cipher's decision serves as an example of how former Bitcoin miners are funding their AI deployment projects. When construction costs rise, they turn to the convertible bond market.
Who is Paying for the Barber Lake Project Overruns?
The overruns, which Cipher is now covering, relate to September 25. Cipher announced on September 25-th that the service life of the Barber Lake facility would be doubled—to 20 years.