Hut 8 Mining's Site in Alberta Running at 15% Hashrate Due to Electrical Issues, Restoration Expected in 10-12 Weeks

05/09 12:05

Hut 8 Mining's site in Drumheller, Alberta is currently experiencing electrical issues, causing it to run at only 15% of its installed hashrate. The firm expects restoration to take place in 10-12 weeks. The issues were first announced in March and are caused by high energy input levels and spikes in energy prices. Hut 8 is working to repair machines, hire more staff, and has implemented firmware to decrease the voltage of the power supply. The Drumheller site likely accounts for as much as 0.9 exahash/second (EH/s) of Hut 8's computing power.
bullishbullishbullishBullishbearishbearishbearishBearishLikeShare
DisclaimerThe content above does not represent HTX's positions.HTX does not provide any trading recommendations.

All Comments0LatestHot

avatar
LatestHot